Sprint report
In this section, we're going to talk about the Sprint report. We'll talk about what it is, and we'll talk about how to read it. In the Sprint report, there's a summary of the Sprint iteration. It's going to show us the burndown, the work that's been completed, the work that wasn't completed, and any work that was added and removed during the iteration.
Let's take a look at JIRA, and get more information about a Sprint report. Do we remember the demo project that we used? For going into reports, we can click on Reports
on the left, and then we can take a look at our Sprint report:

Sprint report
Keep in mind that our burndown is not going to be beautiful because this was a one-day Sprint. Normally, the burndown would be more appropriate based on the iteration length of our we Sprint. But let's pay attention to the bottom. As we can see in the preceding screenshot, we've got the Completed Issues
(items that were completed during this Sprint). If we look at any issues that were added...